Standish Court Weekly Site Update | First Floor Painted & Drylining in Full Swing!

  • Writer: NEWS
    NEWS
  • Jul 11
  • 4 min read

Updated: Sep 2

Exciting progress is unfolding at Standish Court, one of Chorley’s most anticipated property developments! This week marks a major step forward as the first floor is fully studded and spray-painted, and drylining continues at full throttle across the remaining floors.


Whether you're an investor, a future homeowner, or simply following the build, this update provides a detailed look into the transformation taking place inside this stunning development. From sharp internal finishes to robust electrical installations, things are coming together at Standish Court.


Behind the Scenes: See the Progress for Yourself

Want to see the transformation in real-time? We’ve captured this week’s highlights in a video walkthrough.


Watch the latest progress video here:

Don’t forget to like, subscribe, and turn on notifications to stay updated with the latest videos and site news.


What’s New This Week at Standish Court?

Spray Paint (Standish Court)

Construction is entering a dynamic phase with visible progress across multiple disciplines. Here’s a summary of the key updates from this week:


First Floor: Fully Studded and Spray-Painted

Drylining Underway on All Remaining Floors

Electrical Installations Advancing Across Levels





First Floor Progress: Stud Work + First Coat of Paint Complete

This week, the entire first floor of Standish Court is now fully studded, marking a critical milestone in the internal fit-out stage. Each apartment’s walls and internal layouts are clearly defined, giving an early glimpse of the finalized room dimensions and space flow.

First coating (Standish Court)

Even more exciting, the first coat of paint has been spray-applied throughout the first floor. This not only provides visual clarity but also brings the design vision closer to reality. The choice of spray painting ensures a smooth, even application, enhancing the efficiency and quality of the overall finish.



“The transformation is incredible. You can now walk into each apartment and start to visualize the final product.”


Drylining in Full Swing Across Remaining Floors

While the first floor looks more polished, the drylining teams are hard at work on the remaining four floors. This includes framing, fixing plasterboards, and beginning preparation for future painting.


Drylining plays a vital role in shaping the interiors—it sets the stage for insulation, smooth finishes, and soundproofing. Each week, as this process moves upwards, the Standish Court build is closer to completion.

Insulation

Why Drylining Matters:

  • Defines living spaces with accuracy

  • Helps with acoustic performance

  • Improves energy efficiency with insulation

  • Prepares walls for final decorative finishes


Electrical Installations: Powering the Future

Electrical Installation (Standish Court)

Alongside the structural progress, the electrical team has been making strong headway. Wires, conduits, and key systems are being installed at a rapid pace across all floors.


Electrical works

Every unit at Standish Court is being built to modern, high-spec standards, meaning future residents can enjoy:

  • USB charging sockets

  • LED energy-saving lighting

  • Smart home readiness

  • Enhanced wiring for high-speed internet



“We’re laying the groundwork now so that residents walk into a home that’s ready for the digital age.”


Internal Layouts Taking Shape

As walls are studded and coated, the real character of each apartment is beginning to show. From open-plan living areas to spacious bedrooms, each home is being thoughtfully arranged to maximize light, space, and flow.


This week’s walk-throughs revealed how:

  • Kitchens will seamlessly integrate into living areas

  • Bedrooms will have optimal placement for natural light

  • Hallways and entryways are being streamlined for comfort


These internal layouts are designed for both aesthetics and practicality, perfect for modern lifestyles.


Why Investors & Homeowners Should Be Watching
Investors and business

If you’ve been on the fence about investing in Standish Court or looking for a future home in Chorley, now’s the time to pay attention.


Key Reasons to Get Involved:

  • Construction is ahead of schedule

  • Demand for high-spec homes in Chorley is growing

  • Modern design + quality finish = long-term value

  • Great potential for rental yields and capital growth


What’s Coming Next?

Standish Court Construction Stage

Looking ahead, the momentum continues. Here’s what the upcoming weeks have in store:

  • Continued drylining on upper floors

  • Second coat of paint on the first floor

  • Electrical testing and installation of sockets/switches

  • First, fix the plumbing

  • Window trims and door frame installations


Each of these steps brings the project one step closer to practical completion.



📞 Book a Private Tour or Register Your Interest

CTA for Standish Court Apartment

We’re now offering private on-site tours for interested buyers and investors. This is your chance to walk through the site, view progress firsthand, and envision your future home or investment property.

👉 Click here to book a viewing or register your interest.

📬 Or email us directly at sales@mydbr.co.uk



Why Standish Court?
Standish Court Top Side View

Located in the heart of Chorley, Standish Court offers:

  • A central location with great transport links

  • Proximity to local parks and nature trails

  • Easy access to shopping, dining, and schools

  • Beautiful brick architecture with contemporary interiors


Each apartment is designed to meet the highest modern standards, making it ideal for both professionals and families.


Summary: This Week’s Key Milestones


Let’s recap the major highlights:

✔️ First floor now studded and spray-painted

✔️ Drylining is actively underway across the upper floors

✔️ Electrical installations progressing strongly

✔️ Internal layouts are becoming more visible and defined

✔️ On-site work remains on schedule and full of momentum


Stay Connected with Standish Court

real estate agent

Follow our journey and be part of the transformation by:


The progress is real, the finishes are impressive, and the future of Standish Court is looking bright.


👉 Act now—secure your place in Chorley’s most exciting new development!


 
 

Subscribe to Our Weekly Newsletters

​Get our latest news, insights, and expert updates on UK Property Investments and Projects, and helping you understand what truly matters when it comes to UK Property Investment Opportunities.

Thank you for subscribing!

Blog post

dbr investment group ltd for UK Property Investment

Since 2017, DBR Investment Group has been driving UK property investment, completing 20 projects across 15 vibrant cities and towns in England and Wales. Registered Company No. 11707466.

Follow Us 

  • Threads
  • Instagram
  • Facebook
  • LinkedIn
  • X
  • YouTube
  • TikTok
PRS Logo for UK Property Investment
Citation ISO for UK Property Investment
SMAS worksafe for UK Property Investment
NRLA Landlord Member -for UK Property Investment
ICO for UK Property Investment

Contact Information

Phone: 

0161 459 4292

Address: 

The Old Carnegie Library, 361 Ormskirk Road, Pemberton, Wigan, UK, WN5 9DQ

© 2014 - 2025 DBR Investment Group | Privacy Policy

bottom of page